Custom Table SOP

Created by Gloria Payak Robert, Modified on Sat, 28 Feb at 4:30 PM by Gloria Payak Robert

Click here to access the excel file


No.FieldsDefinition/PurposeDoes C&P team need to fill this?
1RAW16
System generated numberNot required
2Sourcing Project IDThe unique identifier for the Ariba sourcing projectYes
3Supplier (Vendor ID)The supplier that have been awarded items or lots in a sourcing eventYes

4Sourcing Event IDThe unique identifier for the Ariba sourcing eventYes

5Procurement ModeThe method of procuring goods/services and it is a custom field. Example includes goods, services, tender (invited), tender (open) etcYes

6Procurement CategoryGrouping of similar Goods or Services and it is a custom field. Example includes goods, services, works etc.
Yes

7Sourcing Project TitleThe name of the project that is used to manage sourcing projects.
Yes

8Sourcing Event TitleThe name of the event that is used to manage sourcing events.
Yes

9Create onThe date on which the custom table line was created in S/4 HANA
Not required

10Created atThe time at which the custom table line was created in S/4 HANA
Not required

11OA Validity fromIt is equivalent the field "Contract Effective Date" in Ariba. It refers to the start date of the validity period for a Contract/Outline Agreement (OA)
Yes
12OA Validity toIt is determined by calculating the Contract Effective Date plus the Contract Duration (in months) in Ariba. It represents the end date of the validity period for a Contract or Outline Agreement (OA).
Yes

13PO Delivery DateThe date on which the goods or services ordered in a Purchase Order (PO) are expected to be delivered. Typically for Quotation sourcing project in SEB.
Yes

14RFQ

"It refers to Request for Quotation and to solicit price quotes and terms from one or more potential vendors for specific materials or services.

It is not required for legacy projects that do not have RFQ IDs.

It is required for projects that have RFQ IDs."

Not required for legacy projects
*CBS decided to do RFQ validation meaning will not be able to save the custom table if the RFQ ID is invalid. Thus for legacy project, empty RFQ ID is allowed
15Changed OnThe date on which the sourcing project/event is updated in Ariba and overrides the corresponding information in S/4HANA.
Not required
16Changed atThe time at which the sourcing project/event is updated in Ariba and overrides the corresponding information in S/4HANA.
Not required

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article